Partners in the Balder field, Vår Energi and Kistos Energy, have taken a final investment decision (FID) on the Balder Next New Wells project in the Norwegian North Sea, which entails a seven-well tieback to the Jotun floating production, storage and offloading vessel (FPSO)…
Ocean Installer has been awarded a major engineering, procurement, construction and installation (EPCI) contract by Vår Energi for the Balder Next New Wells project in the North Sea.The project forms part of Vår Energi's hub development strategy in the Balder area…
Norwegian oil and gas producer Vår Energi has agreed a series of transactions on the Norwegian Continental Shelf that will strengthen its position in core producing hubs, increase ownership in key development projects and provide greater flexibility in capital allocation…
Norwegian oil and gas firm Vår Energi and its partner Kistos Energy have drilled a dry well in the Balder area in the North Sea.The well 25/8-C-23 D, dubbed Prince Updip, was drilled in production license 027, from the Ringhorne platform, just over 200 kilometers west of Stavanger…
Norwegian oil and gas firm Vår Energi has put the Balder Phase V project into production, while also completing of Åsgard Low Pressure Production Phase 3 (LPP3) scheme, bolstering its North Sea production.With the Åsgard LPP3 project start-up scheduled for December…
The Norwegian Offshore Directorate (NOD) has granted Vår Energi a drilling permit for a wildcat well in the North Sea field.The permit is for wellbore 25/8-C-23 D in production license 027.Vår Energi is the operator of the license, with 90% working interest…
Equinor has scrapped plans to cut greenhouse gas emissions by connecting several offshore platforms to Norway's onshore power grid, the company told the government on Friday, citing soaring costs.The oil and gas sector is Norway's largest source of climate emissions…
Norwegian oil and gas company Vår Energi has informed that the Jotun floating production, storage and offloading (FPSO) unit, deployed at the Balder field in the North Sea, reached peak production ahead of schedule.The Jotun FPSO is now producing…
Norwegian oil and gas firm Vår Energi has completed the drilling of second well at the Balder field in the North Sea using COSL Drilling Europe’s COSL Pioneer semi-submersible drilling rig.COSLPioneer delivered the second well, BT-4, at the Balder field for Vår Energi…
Vår Energi and license partner Kistos Energy Norway have reached the final investment decision (FID) for the Balder Phase VI project in the Balder area, off Norway.The fast-track development will be a key contributor to sustaining long term…
Norwegian oil and gas company Vår Energi has achieved a significant milestone by reaching a production level of 400 thousand barrels of oil equivalent per day (kboepd), ahead of schedule.The company said it is also on track to produce around 430 kboepd in the fourth quarter this year…
The new deployment marks a new chapter in offshore operations, where full wireless coverage lays the foundation for real-time data processing, seamless sensor integration and smarter, safer platforms. The Jotun FPSO at the Balder Field on the…
Vår Energi and Kistos Energy Norway have started production through Jotun floating production, storage and offloading (FPSO) unit at the Balder field in the North Sea.The production from Jotun FPSO marks the extension the life of the first production license…
Equinor and its partners have drilled a dry wildcat well on the Lit prospect in the North Sea.The well 25/11-30 S was drilled in production license 169, which was awarded in the 13th licensing round on the Norwegian continental shelf (NCS) in 1991…
Vår Energi has started the tow out of the Jotun floating production, storage and offloading vessel (FPSO) from the Worley Rosenberg yard to the Balder field, which is on schedule for production start by the end of the second quarter of 2025…