Nord Stream 2 Delays Pipe Laying Works Restart

©Nord Stream 2
©Nord Stream 2

The Russia-led Nord Stream 2 consortium is not resuming work to complete the subsea gas pipeline to Germany just yet, daily Handelsblatt reported on Friday, citing a consortium spokesman, amid pressure from Washington to halt the project.

A Danish maritime regulator said last month construction work would resume in Danish waters in mid-January, with a vessel called Fortuna laying the pipes.

"We have permission from the Danish energy agency to start work from Friday. However, this does not mean that we will also resume laying pipes on Friday," Handelsblatt quoted the Nord Stream 2 spokesman as saying.

The consortium will probably be able to say at the end of January or in early February when work will resume, the spokesman said, according to the report.

Nord Stream 2 has not responded to requests for comments.

According to Refinitiv Eikon shiptracking data, the Fortuna was anchored near the German port of Rostock on Friday.

Construction of Nord Stream 2 was initially halted in December 2019 following the threat of sanctions from the United States, which wants to cut Europe's dependence on Russian energy and sell its own liquefied natural gas to the region.

The construction of a 2.6-km long portion of the pipeline in Germany's shallow waters was resumed and finished last month with the help of the Fortuna.

Nord Stream 2, designed to double capacity of the existing undersea Nord Stream gas pipeline from Russia to Germany to 110 billion cubic metres (bcm) per year, more than half of Russia's overall pipeline gas exports to Europe.

Separately, Germany's maritime authority said on Friday it had given Nord Stream 2 permission to lay pipelines in its exclusive economic zone from the end of September to the end of May following an application from the consortium in June 2020.

The consortium, led by Russian gas giant Gazprom, still has to lay more than 100 km (62 miles) of the pipeline, which will have annual capacity to pump 55 bcm of gas. More than 90% of the project has been completed.

Gazprom's western partners in the project, which is estimated to cost 9.5 billion euros ($11.5 billion), are Germany's Uniper and BASF's Wintershall Dea ; Anglo-Dutch oil major Shell; Austria's OMV , and France's Engie. 

(Reporting by Kirsti Knolle in Berlin, Christoph Steitz in Frankfurt and Vladimir Soldatkin in Moscow. Editing by Thomas Seythal and Mark Potter)

 


Current News

Hess Sets Date for Shareholder Vote on Chevron Merger

Hess Sets Date for Shareholder

US Releases Offshore Wind Liftoff Report and Promises Funding

US Releases Offshore Wind Lift

US Interior Department Finalizes Offshore Renewable Energy Rule

US Interior Department Finaliz

US Plans 12 Offshore Wind Auctions Over Five Years

US Plans 12 Offshore Wind Auct

Subscribe for OE Digital E‑News

Offshore Engineer Magazine