First Dussafu DTM-4H Production Well Completed

Published

Panoro Energy announced the successful completion of the DTM-4H well, the first of the phase 2 Tortue development wells, offshore Gabon.

The well was drilled with the Borr Norve jackup drilling rig in 116 meters water depth as a horizontal production well in the Gamba reservoir. A long horizontal section of good quality oil saturated Gamba sands was drilled and completed and the subsea tree installed ready for hook up early next year.

The rig has now moved to the DTM-5H well location, the second of the four phase 2 production wells, and the DTM-5H well was recently spud.

First production from the phase 2 Tortue wells is planned for March 2020 with all four phase 2 wells expected to be online by June 2020.

Current News

Fugro Arms Survey Fleet Against GPS Jamming After $28M Earnings Hit

Fugro Arms Survey Fleet Agains

Norway Pours $424M Into Floating Offshore Wind Development

Norway Pours $424M Into Floati

Petrobras Strikes More Oil in Ultra-Deep Waters Off Brazil

Petrobras Strikes More Oil in

BP Posts Five-Year Profit High as Iran War Fuels Energy Windfall

BP Posts Five-Year Profit High

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine