NFE's Louisiana Offshore LNG Plant Start-up Slips to 2H 2023

Scott DiSavino
Tuesday, November 1, 2022

U.S. firm New Fortress Energy Inc's proposed Louisiana offshore liquefied natural gas (LNG) facility likely will not begin operation until the second half of 2023, people familiar with the matter said on Monday.

The 2.8 million tonne per year export project initially was proposed to start next March but has faced delays during its permit review. U.S. regulators on Friday lifted a stop-clock order. 

The soonest the facility could begin producing LNG, assuming no further delays, is the second half of next year, one of the people said. The U.S. Department of Transportation's Maritime Administration (MARAD) in August had stopped the clock on a 356 day review process, citing information gaps in the application. 

"They were not going to make the first half of 2023 deadline as soon as they got the stop-clock letter," Christine Tezak, managing director at energy consulting firm ClearView Energy Partners LLC, told Reuters on Monday. 

"If New Fortress gets its resume-clock letter today, the earliest they would have approval is early June...so long as the clock is not stopped again and they get all their other approvals," Tezak said. 

It would take a further two months after approval is received to begin commercial processing. 

The company has said it will take about 14 to 16 months to fabricate eachFast LNG unit and another 4 to 6 months to install, hook up and commission the units at their offshore sites. 

Last week, NFE said it finalized a deal with Mexico state power and gas utility Comision Federal de Electricidad (CFE) to deploy multiple offshore LNG units.



Categories: Offshore Energy LNG Industry News Activity North America FLNG

Related Stories

Chartwell Marine Grows CTV Build Pipeline for Offshore Wind Market

Ocean Charger for Offshore Wind Vessels Proves a Success

Saipem Completes Ops on LNG Scheme Offshore Greece

Current News

New York Not Moving Forward With Three Offshore Wind Farms

DNV Awards Certificates for Fortescue’s Dual-fueled Ammonia-powered Vessel

Energy Storage on O&G Platforms - A Safety Boost, too?

Türkiye Aims to Drill for Oil Off Somali Coast Next Year

Subscribe for OE Digital E‑News