VBMS completes umbilical installation

Published

VBMS completed a remote platform tieback project - platform L8-P4 to L6-B - for Wintershall Noordzee B.V. in the North Sea.

Image of the Ndurance. From Boskalis.

The scope of work for VBMS included the engineering, installation and burial of a 19.5km umbilical, at a water depth of 29m.

The L6-B platform is a remote tieback to L8-P4 in the L blocks in the Dutch sector of the North Sea, located approximately 30km northwest of Den Helder. The platform is the newest addition to the Wintershall offshore assets in this sector.

The J-tube pull-ins were performed directly from the Boskalis cable-laying vessel Ndurance using its quadrant system without any interruption or temporary lay-down of the umbilical. VBMS deployed a specialized burial vessel for the post-installation jet trenching. A follow-up as-laid survey of the umbilical route verified that the burial exceeded the requirements in order to ensure optimal protection of the umbilical.

Current News

Saipem, Subsea 7 Undergo EU Antitrust Investigation

Saipem, Subsea 7 Undergo EU An

Baltic Power Offshore Wind Farm Delivers First Electricity to Polish Grid

Baltic Power Offshore Wind Far

Eni Enlists OneSubsea for Deepwater Umbilical Supply off Indonesia

Eni Enlists OneSubsea for Deep

Petrobras Concludes Acquisition of São Tomé and Príncipe Offshore Block

Petrobras Concludes Acquisitio

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine