VBMS completes umbilical installation

Published

VBMS completed a remote platform tieback project - platform L8-P4 to L6-B - for Wintershall Noordzee B.V. in the North Sea.

Image of the Ndurance. From Boskalis.

The scope of work for VBMS included the engineering, installation and burial of a 19.5km umbilical, at a water depth of 29m.

The L6-B platform is a remote tieback to L8-P4 in the L blocks in the Dutch sector of the North Sea, located approximately 30km northwest of Den Helder. The platform is the newest addition to the Wintershall offshore assets in this sector.

The J-tube pull-ins were performed directly from the Boskalis cable-laying vessel Ndurance using its quadrant system without any interruption or temporary lay-down of the umbilical. VBMS deployed a specialized burial vessel for the post-installation jet trenching. A follow-up as-laid survey of the umbilical route verified that the burial exceeded the requirements in order to ensure optimal protection of the umbilical.

Current News

Exploration Well in Black Sea Offshore Block Comes Up Dry

Exploration Well in Black Sea

Mammoet to Handle Substation Load-Outs for TenneT 2GW Program

Mammoet to Handle Substation L

Germany Acquires Minority Stake in TenneT for $3.9B

Germany Acquires Minority Stak

Japan’s JERA Agrees Long-Term LNG Supply from Middle East

Japan’s JERA Agrees Long-Term

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine