Goliat FPSO living quarters lifted

Published

Eni Norge provides this video clip of the living quarters being lifted into place at the Goliat FPSO. Lifting the modules, required the use of a crane with the capacity to lift 1.6 million kg, ENI said. The five-level living quarters modules weighed 1100 tonnes, using 85% of the crane's lifting capacity. The FPSO is under construction at Hyundai Heavy Industries' yard in South Korea. Find more about the lifting operations here: http://www.eninorge.com/en/Field-development/Goliat/Milestones/Living-quarters-are-lifted-into-place/