Polarled crosses the Arctic Circle

On 21 August the Polarled gas pipeline crossed 66° and 33 minutes north of the equator becoming the first pipeline to take the Norwegian gas infrastructure across the Arctic Circle. This will open a new gas highway from the Norwegian Sea to Europe.


 
Image: This piece of pipe marks Polarled’s crossing of the Arctic Circle/Statoil

The 482km long and 36in wide pipeline will run from Nyhamna in western Norway to the Aasta Hansteen field in the Norwegian Sea. The world’s largest pipelaying vessel, Solitaire from Allseas, is carrying out the job and is advancing slowly, exactly 24.4m at a time, every sixth minute or so, around the clock.

Good progress

During the start-up in March the pipeline was pulled in to Nyhamna. During September the vessel will arrive at the Aasta Hansteen field, if weather permits. Even early in the autumn high waves and strong wind leading to interruptions must be expected. The weather has been good for a long period now.

“We are progressing well at the moment, conditions have been good for more than 50 days in a row, and at the end of July we set a record of laying 4.8km of pipes in one day,” said Kenneth Aksel Kristensen, one of Statoil’s company representatives on board the vessel.

Being from northern Norway Kristensen is particularly proud of helping lay the very first pipeline across the Arctic Circle. Polarled will also be the deepest pipeline on the Norwegian continental shelf – by the Aasta Hansteen field the water depth is 1260m. Furthermore, it will be the first time a 36in wide pipe is laid in such deep waters anywhere in the world.

Shuttle traffic

The vessel is a huge, well-oiled pipelaying machine which needs constant supply of pipes. Every pipe is 12.2m long and the vessel is laying around 4km of pipes a day. This means that it needs a supply of more than 300 pipes a day, filling two to three boats every day.

Two cranes are working hard like busy ants as they are lifting hundreds of pipes on board the vessel. One by one the 12-15-tonne heavy pipes are lifted on board – and when one boat is empty it only takes a few hours before the next boat arrives with more pipes. There are six boats in shuttle traffic transporting pipes.

“The pipes arrive from Wasco in the city of Mo i Rana, where they are coated,” explains Kristensen. “This means that they have been given a concrete layer to protect them from trawling and make them heavier.”

Assembly line

When a pipe is lifted on board the Solitaire it enters a huge assembly line. The pipe is sent from station to station through the factory of the 397m long and 41m wide vessel, where specialized operators perform their tasks. They are welding, checking, welding some more and checking some more before the welded joints are protected and the pipe becomes part of the long tail behind the Solitaire.

The pipeline is not laid in a straight line.

“We have examined the seabed thoroughly in advance to find the best route and also to avoid corals and large rocks,” says Arne Fosse, Statoil’s head of the Polarled construction work.

Saving money

In his office in Stavanger project manager Alfred Øijord has reason to smile. After some periods of bad weather right after the pull-in to Nyhamna in March, the project is progressing well – also financially.

“We are currently expecting to deliver way below budget,” said Øijord. “The original investment budget for the pipeline project was NOK 11.1 billion. We are now expecting an investment level of around NOK 7.5 billion, due to good planning, good market knowledge and good execution. We have also had favorable market conditions with regard to capacity and price.”

Building for the future

At start-up the gas from Aasta Hansteen will be the only gas passing through Polarled, but the pipeline has a diameter of 36in and capacity for more gas:

“We have therefore installed six connection points, call it future slip roads to the new gas highway,” says Håkon Ivarjord, Statoil’s project venture manager for the Polarled development project. “Polarled will open up for gas export to Europe from a completely new gas province, and with the infrastructure in place it will also be more attractive to explore the surrounding area.”

24-hour operation

The Solitaire crew is working around the clock. It takes around 90 minutes from a pipe is lifted on board and enters production until it has become part of the ever-extending Polarled pipeline. There are 410 people on board the vessel, including two asset owner representatives from Statoil and eight people from DNV GL – who are also part of the day and night operation.

In a control room aft, Max Misund is busy studying his computer screen – around every sixth minute he receives the result of the automatic ultrasound inspection made inside the vessel. Also this weld is approved.

 “We have now checked more than 14,000 welds and the repair rate is 0.6%. That is an excellent result!” said Misund. He went on to say that the welding quality was good.

The pipelaying work had to wait on weather for a couple of days, and gave the crew a welcome break.

“Laying several hundred kilometers almost without weather interruptions is very unusual. It is good to have a break to perform necessary maintenance on the pipelaying equipment, and not least to give the crew a welcome break before completing the pipelaying in 1260m of water,” concludes Arne Fosse.

This autumn the new highway for gas from the Norwegian Sea will be ready for use – on time and well below budget.

Current News

ASL to Work on Metocean Data for Offshore Wind Project in Atlantic Canada

ASL to Work on Metocean Data f

RWE Gets Clearance for 100MW Electrolyzer for OW-to-Hydrogen Production

RWE Gets Clearance for 100MW E

DOF Group Completes Acquisition of Maersk Supply Service

DOF Group Completes Acquisitio

Tyra II Facilities to Operate at Full Technical Capacity Sooner Than Expected

Tyra II Facilities to Operate

Subscribe for OE Digital E‑News

Offshore Engineer Magazine