Gemini foundations installed in record time

Published

Van Oord has completed the installation of the 150th foundation at the Gemini Wind Park in a record time of 3.5 months.

On the 1 of July 2015, Van Oord’s newbuild installation vessel Aeolus, together with Swire Blue Oceans Pacific Osprey, started installation and the last foundation was installed on the 17 October, one month earlier than scheduled.

On 1 of February, 2016 both vessels will return to the project, completely modified for the installation of the 150 wind turbines. They will sail from Esbjerg in Denmark, where the wind turbines are produced and stored at Siemens, directly to the Gemini Wind Park.

Read more

Doubling Dutch wind capacity

Current News

Petronas Names ‘World's First’ Nearshore FLNG Facility

Petronas Names ‘World's First’

Oil Falls as Supply Glut Concerns Overshadow Hormuz Shipping Risks

Oil Falls as Supply Glut Conce

Windcat Expands Offshore Fleet with Second Damen Multi-Purpose Vessel

Windcat Expands Offshore Fleet

NextGeo Gets $12.7M Offshore Survey Job for Spain-France Hydrogen Link

NextGeo Gets $12.7M Offshore S

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine