Gemini foundations installed in record time

Van Oord has completed the installation of the 150th foundation at the Gemini Wind Park in a record time of 3.5 months.

On the 1 of July 2015, Van Oord’s newbuild installation vessel Aeolus, together with Swire Blue Oceans Pacific Osprey, started installation and the last foundation was installed on the 17 October, one month earlier than scheduled.

On 1 of February, 2016 both vessels will return to the project, completely modified for the installation of the 150 wind turbines. They will sail from Esbjerg in Denmark, where the wind turbines are produced and stored at Siemens, directly to the Gemini Wind Park.

Read more

Doubling Dutch wind capacity

Current News

Cyprus Seeks Improvements to Chevron-led Plans for Offshore Gas Field

Cyprus Seeks Improvements to C

Equinor Seeks to Revive Costly Norway, Canada Oil Prospects

Equinor Seeks to Revive Costly

France Launches Call for 2.5 GW of Offshore Wind Tenders

France Launches Call for 2.5 G

ConocoPhillips Misses Quarterly Profit Estimates

ConocoPhillips Misses Quarterl

Subscribe for OE Digital E‑News

Offshore Engineer Magazine