PSA audits Goliat facility

Published

From 30 January to 3 February 2017, the Petroleum Safety Authority Norway (PSA) carried out an audit of the planning and execution of work on hydrocarbon-carrying systems for Eni's Goliat facility.

The audit was a sub-activity of an audit series that will continue throughout 2017. The background to this sub-audit includes the seven hydrocarbon leaks that occurred in 2016.

The objective of the audit was to follow up on how Eni is managing risk associated with work on hydrocarbon-carrying systems, and how the compensatory measures implemented for this area are working.

The audit detected one non-conformity associated with knowledge of the status of safety systems.

In addition, improvement points were detected in connection with:

  • Management of competence for personnel with responsibilities and duties linked to hydrocarbon-carrying systems.
  • Dissemination of information
  • Procedures
  • Key locks on valves liable to be incorrectly operated.

Eni has been given a deadline of 12 May 2017 to report on how the non-conformity will be dealt with and how the improvement points will be assessed.

Current News

CRP Subsea Secures Cable Protection Contract for Offshore Wind

CRP Subsea Secures Cable Prote

Nordic Investors to EU: Nix Notion of Arctic Drilling

Nordic Investors to EU: Nix No

Export Curbs Should not Harm Australia's Biggest LNG-producing State

Export Curbs Should not Harm A

NOPSEMA Releases Australia’s Offshore Energy Industry Performance Report

NOPSEMA Releases Australia’s O

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine