The first liquefied natural gas (LNG) shipment from the giant Ichthys project in Australia arrived at Inpex's Naoetsu LNG receiving terminal in northern Japan on Wednesday, the Japanese operator of the project said.The LNG vessel Pacific Breeze…
French oil and gas major Total said on Tuesday that the first cargo of liquefied natural gas (LNG) cargo from Australia's Ichthys LNG project has been exported following the production start-up at the end of July.Ichthys LNG, with reserves of…
Inpex Corporation announced the departure of its first shipment of condensate from the Inpex-operated Ichthys LNG Project.The cargo departed from the Project’s massive offshore floating production, storage and offloading facility - the Ichthys Venturer –moored in the Browse Basin…
Audrey Leon takes a look through some of the industry’s biggest ongoing projects by capex in 2017. Five of the 10 biggest projects by capex were offshore projects in 2017, led by Inpex’s Ichthys LNG project offshore Australia. Ichthys…
Japan's Inpex has been awarded an exploration permit for Release Area WA-532-P, close to its Ichthys LNG development, in Australia’s 2016 Offshore Petroleum Exploration Acreage Release. Inpex Browse will hold a 100% participating interest in the block…
Wood Group secured a new, five-year contract with Inpex Operations Australia (Inpex Australia) to provide subsea engineering services for the integrity of the Ichthys LNG Project, offshore Western Australia. Image from Inpex…
Wood Group has won a five-year contract with INPEX Operations Australia to provide subsea engineering services for the integrity of the Ichthys LNG Project, offshore Western Australia. The operations of all subsea assets and the gas export pipeline will be supported under the contract…
The INPEX-operated Ichthys LNG Project’s floating production, storage and offloading facility (FPSO) has been safely moored today in the Ichthys field, 220km off the north coast of Western Australia. The 336m-long FPSO, Ichthys Venturer…
The Ichthys Venturer floating production, storage and offloading (FPSO) facility has arrived in Australian waters today (14 August), as Inpex gears up to begin hook-up and commissioning activities. The Ichthys Venturer at the DSME shipyard…
The INPEX-operated Ichthys LNG Project’s floating production, storage and offloading (FPSO) facility Ichthys Venturer has set sail for Australia. The 336m-long long ship-shaped, offshore facility has started a 5600km voyage that will take about one month to complete…
Marine and offshore engineering consultancy Aqualis Offshore has successfully completed its position keeping role for the Ichthys central processing facility (CPF), which is now moored to a storm safe condition in Australian waters. On 29 May 2017…
Inpex's Ichthys Explorer, the world's largest semisubmersible platform safely arrived in the Australian waters of the Browse basin, marking a milestone for the Ichthys LNG project. The Ichthys Explorer…
Engineering company Monadelphous Group has been awarded a major, long-term offshore maintenance services contract for Inpex Operations Australia associated with the Ichthys LNG project. The contract is for an initial six years with a further two…
The Ichthys Explorer, the Inpex-operated Ichthys LNG project’s central processing facility (CPF), sailed away from its construction site in Geoje, South Korea in route to the Ichthys field offshore Western Australia, following the completion of shipyard commissioning and preparation work…
Sparrows Group has won a three-year deal to deliver fixed crane maintenance and lifting and rigging services for the Inpex-operated Ichthys liquefied natural gas (LNG) project in Australia. The agreement includes maintenance, servicing and inspection of lifting equipment and cranes…