Tyra II Starts Operating at Full Technical Capacity

Thursday, April 10, 2025

Denmark’s largest offshore gas development, the Tyra hub in the North Sea, has been restarted with full technical capacity achieved on the facilities, following the completion of repairs which impacted the production.

BlueNord, the partner in the Tyra II project along with the operator TotalEnergies and Nordsøfonden, said the continuation of ramp-up of production is currently ongoing.

The development follows the replacement of necessary parts have, and the completion of installation and testing activities.

Since March 4, 2025, the Tyra hub has been restricted to Harald production due to a breaker failure in the electrical high-voltage system, which required replacement equipment.

In February 2025, Tyra II achieved a gas export rate above 200 mmscfpd, marking a commissioning milestone and making a significant step forward in meeting the requirements to start distribution of gas from the project.

At plateau, the Tyra hub will produce 5.7 million cubic meters of gas and 22,000 barrels of condensate per day once fully commissioned and operational.

The gas from the Tyra hub will be delivered to Europe through two export pipelines to Nybro in Denmark and Den Helder in the Netherlands.

Categories: North Sea Industry News Activity Europe Production Oil and Gas

Related Stories

DNO Strikes North Sea Oil Offtake Deals with ExxonMobil and Shell

Vår Energi Starts Up Another North Sea Project

Serica Energy Completes Acquisition of Prax Upstream

Current News

2025: Fascinated with Subsea Discovery

Petrobras strike-hit P-40 Platform shut down after gas leak: union

Aker BP Extends Scarabeo 8 Contract for Offshore Drilling in Norway into 2028

Poland Allocates 3.4 GW Capacity in Offshore Wind Auction

Subscribe for OE Digital E‑News