BW Opal FPSO Starts Taking Final Shape Ahead of Barossa Assignment

Friday, February 9, 2024
BW Opal FPSO (Credit: BW Offshore)

FPSO leasing company BW Offshore has made progress on the topside module integration for the newbuild floating production storage and offloading (FPSO) unit BW Opal, that will be deployed at Santos' Barossa gas project, offshore Australia.

The teams are keeping busy to complete construction of the topside modules in Dyna-Mac and the turret modules in Profab, with the integration and commissioning activities having started at the Seatrium Tuas Boulevard Yard.

So far, nine of the topside modules (including the E-house) have been lifted and on February 4, the first shipboard turret module was integrated into the hull, according to BW Offshore.

“This was a very critical lift, flawlessly executed using the Asian Hercules III floating crane. The module itself, is an extra source of pride to BW Offshore as the shipboard turret is designed and managed completely inhouse,” BW Offshore said.

The works follow the delivery of the BW Opal’s hull, one of the largest ever built, from the SK Oceanplant (SKOP) yard in South Korea.

The hull has an overall length of 358 meters and a width of 64 meters.  

After completion of integration and commissioning, the BW Opal FPSO will head to Australia to start production at Santos' Barossa project.

Located 300 kilometers offshore Darwin in northern Australia, the Barossa gas field is scheduled for first production in the first half of 2025.

The gas field will be developed via the BW Opal FPSO with six subsea production wells, in-field facilities, and a gas export pipeline tied into the Bayu-Undan to Darwin pipeline system that supplies gas to Darwin LNG.

BW Offshore is responsible for engineering, procurement, construction, installation, and operation of the FPSO.

The Final Investment Decision (FID) for the FPSO for the Barossa project was confirmed by Santos and its partners on March 30, 2021, with a services contract including Operation & Maintenance (O&M) with a firm period of 15 years, and 10 years of options.


Categories: Engineering Industry News Activity Production Asia Australia/NZ Oil and Gas

Related Stories

Valeura Makes Progress with Multi-Well Drilling Campaign in Gulf of Thailand

Valeura Makes Progress with Multi-Well Drilling Campaign in Gulf of Thailand

Santos and QatarEnergy Agree Mid-Term LNG Supply

Santos and QatarEnergy Agree Mid-Term LNG Supply

One Shelf Drilling Rig Up for New Job in India, Other for Disposal

One Shelf Drilling Rig Up for New Job in India, Other for Disposal

Current News

Iberdrola Picks Up $4.9B to Finance 1.4GW UK Offshore Wind Farm

Perenco Brings Woodside’s Trinidad Oil and Gas Assets Into Its Fold

Vallourec Brings CNOOC, Petrochina as New Clients in Iraq

Germany’s SEFE Inks Three-Year LNG Supply Deal with ADNOC

Subscribe for OE Digital E‑News

Offshore Engineer Magazine