Leviathan on Track for December Startup

Sunday, November 10, 2019

The mega Leviathan gas field offshore Israel is on track to begin production in December, ahead of schedule and below budget, operator Noble Energy said.

The Leviathan project is 96% complete after production decks were installed on the jacket in the third quarter, the company said in its third quarter report.

Full hookup of the platform and living quarters, as well as platform commissioning, continues to progress toward first production in December. 

The Leviathan field – holding 33 trillion cubic feet (Tcf) of resources in place (22 Tcf recoverable), with potential for more natural gas discoveries as well as large-scale crude oil discoveries at greater depths – is among the world’s largest natural gas finds.

Project spend was more than $30 million under guidance in the third quarter, and total gross capital for the project has been reduced $150 million to $3.6 billion, Noble Energy said.

During the third quarter, Noble Energy and its partners amended sales agreements for the delivery of natural gas from the Leviathan and Tamar fields to Dolphinus Holdings Limited in Egypt. The amended agreements now provide for total combined firm contract quantities of 3 Tcf of natural gas.

Categories: Natural Gas Engineering Activity Production Construction Installation

Related Stories

CNOOC Puts New South China Sea Development Into Production Mode

Britain Eases Opposition to New Oil, Gas Permits

ADES Completes Acquisition of Shelf Drilling

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Subscribe for OE Digital E‑News