Caribbean FLNG time-lapse

OE Staff
Monday, October 5, 2015

In this video, EXMAR shows a time-lapse video of the construction of the Caribbean FLNG at Wilson Shipyard, located in Nantong China.

In EXMAR's 2Q 2015 report, the company revealed that pre-commissioning of the Caribbean FLNG ws proceeded as planned for 3Q, with an expected delivery date during 1Q 2016.

A delay with the Caribbean FLNG was announced in February in EXMAR's 1Q 2015 report. Operator Pacific Rubiales Energy delayed start-up due to unfavorable energy market conditions.

In 2012, EXMAR was contracted to build, operate, and maintain the floating liquefaction, re-gasification, and storage unit (FLRSU), which will serve the La Creciente field in Colombia’s lower Magdalena Valley basin for 15 years. Wison Offshore and Marine’s fabrication yard in Nantong, China, constructed the vessel, which undocked from the shipyard in late November.

The vessel will be able to convert 69.5 MMcf/d of natural gas from the field into LNG. The barge, which will measure 140m x 32m x 18m, and will be able to store 14,000cu m in onboard tanks. The processing unit will be moored to a jetty in 15m water depth. Topsides equipment will weigh about 5000t. Black and Veatch was contracted to build the liquefaction plant.

Read more:

Global FSRU demand ramps up

Caribbean FLNG delayed

EXMAR orders second FLNG unit

Categories: Asia Natural Gas Construction FLNG China

Related Stories

Akastor’s Subsidiary Wins $101M Case Against Seatrium's Jurong Shipyard

ONGC Hires Consortium to Deliver FEED Work for Bay of Bengal Oil Field

Woodside and Partners Appoint Wood for Greater Sunrise Gas Concept Study

Current News

Talos Energy Makes Leadership Team Changes

SOVs – Analyzing Current, Future Demand Drivers

Equinor Cleared for Drilling Ops at Johan Castberg Field with Transocean Enabler Rig

Skanska Set for South Brooklyn Marine Terminal Buildout

Subscribe for OE Digital E‑News