Gemini foundations installed in record time

OE Staff
Monday, October 19, 2015

Van Oord has completed the installation of the 150th foundation at the Gemini Wind Park in a record time of 3.5 months.

On the 1 of July 2015, Van Oord’s newbuild installation vessel Aeolus, together with Swire Blue Oceans Pacific Osprey, started installation and the last foundation was installed on the 17 October, one month earlier than scheduled.

On 1 of February, 2016 both vessels will return to the project, completely modified for the installation of the 150 wind turbines. They will sail from Esbjerg in Denmark, where the wind turbines are produced and stored at Siemens, directly to the Gemini Wind Park.

Read more

Doubling Dutch wind capacity

Categories: Vessels North Sea Offshore Wind Construction Renewables Installation

Related Stories

RWE, Trump Reach $1.22b agreement to Cancel Offshore Wind Leases

Mermaid Maritime Expands Into US Offshore Market

Vattenfall Secures Rights to Build Two Offshore Wind Farms in Denmark

Current News

DOF Group Announces Subsea Contracts in the APAC Region

Russian Crude Production Falls Lower Amidst Global Uncertainty, Sanctions

TGS and GTI Collaborate on Seismic Acquisition

Tupi Sets Petrobras Production Record

Subscribe for OE Digital E‑News