Keppel on track to deliver Catcher FPSO

OE Staff
Friday, April 28, 2017

Keppel Shipyard says it is on track to deliver the Catcher floating production storage and offloading (FPSO) vessel to BW Catcher following a naming ceremony of the vessel today (28 April).

BW Catcher - the 11th FPSO Keppel has delivered to BW Offshore - is set to go on a seven-year fixed term and 18 years of options contract with UK North Sea operator Premier Oil on the Catcher field.

BW Catcher has 650,000 bo oil storage capacity and 60,000 b/d processing capacity. It has a design life of 20 years without dry docking and will be moored using a submerged turret production at an average water depth of 90m.

Keppel Shipyard's work scope on the FPSO include the installation and integration of topside modules. BW Catcher is scheduled for sailaway from the shipyard in the next few months and is on track to achieve its first oil in 2017.

The Catcher area is expected to produce 96 MMboe, with a peak production rate of around 50,000 b/d. The development includes 22 subsea wells on the Catcher, Varadero, and Burgman fields, tied back to the leased FPSO BW Catcher.

Read more

Premier cuts Catcher costs

Categories: Floating Production Fabrication Europe North Sea FPSO

Related Stories

CNOOC Puts New South China Sea Development Into Production Mode

TGS Secures First OBN Job for 2026 in Europe

UK North Sea Decommissioning Set for Sharp Rise Through 2034

Current News

U.S. Oil Production Still has Growth Potential

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Subscribe for OE Digital E‑News