Video: Fenja Manifold Lift

Published

The template and manifold for the Neptune-Energy-operated Fenja project are currently undergoing factory acceptance testing (FAT) and system integration testing (SIT) in Eydehavn, Norway, as the subsea development ramps up toward planned first oil in 2021.

Watch as a 120-metric-ton production manifold is installed into a 370-metric-ton production integrated template structure.

After testing, the templates and manifolds will be transported to Kristiansund in late July, then transported about 120 kilometers north for installation in the Norwegian Sea in early August. Water depth on site is approximately 325 meters.

Fenja, which is Neptune's first operated field development in Norway, will be a tieback to Njord-A. The 36-kilometer subsea pipeline connecting field and host will be the world’s longest electrically trace-heated pipe-in-pipe.

The development combines two subsea templates with six wells. Three of these will be oil producers, two water injectors and one a gas injector. The gas injector will be converted to a gas producer towards the end of field life.

The field discovery is estimated to contain 97 mmboe 2P reserves.

TechnipFMC is supplying the manifold, trees, controls, riser bases, ETH-PiP, rigid flowlines, flexible risers, umbilical, installation for the project.

Neptune Energy holds a 30% stake in the field, alongside partners Vår Energi, (45%), Suncor (17.5%) and DNO (7.5%).

Current News

BOEM Initiates Process for Potential Mineral Lease Sale Offshore Virginia

BOEM Initiates Process for Pot

Jumbo Scoops Two Offshore Wind Contracts

Jumbo Scoops Two Offshore Wind

Wood Nets Long-Term Maintenance Contract for Rio Grande LNG Facility

Wood Nets Long-Term Maintenanc

TechnipFMC to Supply Subsea Systems for Chevron’s Gas Project off Australia

TechnipFMC to Supply Subsea Sy

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine