Production resumes at Troll C

Production on the Troll C platform in the North Sea has been resumed, following a shutdown on 15 November due to corrosion found in some tanks on the auxiliary system for treating gas.

"A great effort has been made during the weekend to plan the repair work, and we have also looked into alternative production methods," says Rune Adolfsen, head of production on Troll C.

Adolfsen said Statoil arrived at a solution involving reinjection of untreated gas into the reservoir. Production was resumed during the night between Saturday and Sunday.

"We assume that this method will allow us to produce at around 70% of full capacity during the repairs," Adolfsen said.

The duration of the repair work has not yet been clarified.

Current News

Coastal Virginia Offshore Wind Project Has Not Been Delayed

Coastal Virginia Offshore Wind

Oceaneering Signs On for Terradepth's Ocean Data Service

Oceaneering Signs On for Terra

US Oil and Gas Production Rebounds

US Oil and Gas Production Rebo

Macquarie Asset Management to Sell Stake in UK Offshore Wind Farm

Macquarie Asset Management to

Subscribe for OE Digital E‑News

Offshore Engineer Magazine