Production resumes at Troll C

Published

Production on the Troll C platform in the North Sea has been resumed, following a shutdown on 15 November due to corrosion found in some tanks on the auxiliary system for treating gas.

"A great effort has been made during the weekend to plan the repair work, and we have also looked into alternative production methods," says Rune Adolfsen, head of production on Troll C.

Adolfsen said Statoil arrived at a solution involving reinjection of untreated gas into the reservoir. Production was resumed during the night between Saturday and Sunday.

"We assume that this method will allow us to produce at around 70% of full capacity during the repairs," Adolfsen said.

The duration of the repair work has not yet been clarified.

Current News

Chevron Vessel Begins Gas Survey Offshore Greece

Chevron Vessel Begins Gas Surv

ExxonMobil Greenlights $4B Kizomba Revamp with Fresh Discovery off Angola

ExxonMobil Greenlights $4B Kiz

Japan's KEPCO Joins 390MW Polish Offshore Wind Project

Japan's KEPCO Joins 390MW Poli

Türkiye Set for Offshore Seismic Surveys in Pakistan Ahead of 2027 Drilling

Türkiye Set for Offshore Seism

Subscribe for OE Digital E‑News