Production resumes at Troll C

Published

Production on the Troll C platform in the North Sea has been resumed, following a shutdown on 15 November due to corrosion found in some tanks on the auxiliary system for treating gas.

"A great effort has been made during the weekend to plan the repair work, and we have also looked into alternative production methods," says Rune Adolfsen, head of production on Troll C.

Adolfsen said Statoil arrived at a solution involving reinjection of untreated gas into the reservoir. Production was resumed during the night between Saturday and Sunday.

"We assume that this method will allow us to produce at around 70% of full capacity during the repairs," Adolfsen said.

The duration of the repair work has not yet been clarified.

Current News

Technology as Enabler of Energy Security in Offshore Asia

Technology as Enabler of Energ

Akastor’s DDW Offshore Agrees Sale of AHTS Vessel for $23M

Akastor’s DDW Offshore Agrees

Shearwater to Sell SW Baret for Conversion to Source Vessel

Shearwater to Sell SW Baret fo

Rhino Resources Books Saipem Drillship for Work off Namibia

Rhino Resources Books Saipem D

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine