BP extends Maersk Reacher contract

BP Norway has extended its contract for the jack-up Maersk Reacher by two years, from September 2014 to September 2016.

BP Norway holds options to further extend the contract by up to additional four years, taking it out to September 2020.

The estimated value of the two-year extension is US$222 million.

Maersk Reacher is the fourth in a series of four high-efficiency 350ft jack-ups, delivered in 2008-2009.

In 2011, Maersk Reacher was upgraded to comply with relevant requirements in Norwegian shelf regulation, and received an Acknowledgement of Compliance, enabling it to start a three-year firm contract with BP Norway in September 2011.

Current News

ExxonMobil Makes FID on Hammerhead

ExxonMobil Makes FID on Hammer

US Federal Judge Grants Go Ahead for Orsted Offshore Wind Project

US Federal Judge Grants Go Ahe

Chevron, Westlawn Join Anadarko for Oil and Gas Exploration off Peru

Chevron, Westlawn Join Anadark

Multisec Builds One of the Largest C-Hooks for Offshore Wind Project

Multisec Builds One of the Lar

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine