Saudi Aramco says it has set a new record for heavy lift operations in its Arabiyah-Hasbah gas fields project about 150km offshore Saudi Arabia.

The heavy lift barge Lan Jing completed the installation of the Hasbah tie-in platform (TP) using its 7500-ton crane, carrying weight that reached about 5000 tons.

The new tie-in platform was installed as part of the ongoing work to complete the Arabiyah-Hasbah offshore gas fields project, which will produce 2.5 billion scf/d through the Wasit Gas Plant when completed. An intermediate injection platform was also installed.

The Lan Jing has also completed the installation of the Arabiyah field tie-in platform, which weighs 4600-ton, and the intermediate injection platform, which weighs 1800-ton.

The complete development of the two fields encompasses the engineering, procurement, fabrication and installation of a total of 12 wellhead platforms, two tie-in platforms and one injection platform, besides to a 36in. 260km-long export trunkline and approximately 200km of mono-ethylene glycol (MEG) pipelines, 200km of subsea electric and control cables and 40km of offshore flowlines. 

Current News

Turkish Drill Ship Heads to Somalia for First Overseas Mission

Turkish Drill Ship Heads to So

AF Offshore Secures North Sea Decom Job

AF Offshore Secures North Sea

Island Offshore’s Hybrid OECV Hits Water at Vard Yard in Romania (Video)

Island Offshore’s Hybrid OECV

Jumbo Offshore Wraps Up Errea Wittu FPSO Mooring Pre-Lay in Guyana

Jumbo Offshore Wraps Up Errea

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine