Santos GLNG to start 3Q 2015

The US$18.5 billion Santos GLNG project is approaching its 95% complete mark and is expected to produce first LNG around the end of 3Q 2015.

From Santos GLNG.

Previous guidance for first LNG was in 2H 2015.

“The project has continued to go from strength to strength and we have made significant progress on the ground in both 2014 and in the first quarter of this year,” David Knox Santos managing director and CEO said. “The delivery of GLNG will consolidate our strategic LNG portfolio and further position us as a key player in the growing Asian gas market.”

Recent milestones include the introduction of first gas into the LNG plant and the successful firing of the first two gas turbine generators.

GLNG 2014-2015 Snapshot

  • Completed construction of all major gas field processing facilities

  • Completed its 420km pipeline, including a 4.3km undersea pipeline tunnel

  • Installed all 111 modules that make up its two LNG processing trains

  • Hydrotested both of its LNG storage tanks

  • Built its LNG loading jetty

  • Introduction of first gas into the plant and lighting of the flare

  • Successful firing of the first two gas turbine generators

Santos GLNG is a joint venture between Santos (30%), Petronas (27.5%), Total (27.5%) and Kogas (15%).

Read more:

WDS gets Santos GLNG contract

Santos GLNG completes first gas processing hub

First gas fed at Santos GLNG

Current News

Aibel to Provide Maintenance Services for Two Vår Energi’s Oil and Gas Fields

Aibel to Provide Maintenance S

MDL Assists Saipem to Deliver Offshore Campaigns in West Africa

MDL Assists Saipem to Deliver

Woodside and Jera Agree LNG Cargoes Supply for Japan’s Winter Period

Woodside and Jera Agree LNG Ca

Strategic Marine Delivers Fourth Fast Crew Boat to Thai Firm

Strategic Marine Delivers Four

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine