Petrojarl I in for EPC redeployment upgrade

Published

After four months of preliminary work alongside, FPSO Petrojarl I moved on 16 April 2015 into Damen Shiprepair Rotterdam’s 307m long x 47 m wide dry dock no 8 for work to the hull. In all, the vessel will spend a year at DSR before heading off to the South Atlantic. The Teekay managed FPSO arrived at Damen Shiprepair Rotterdam in January 2015.

Petrojarl I. From Damen Shipyards.

DSR was awarded an EPC contract by Teekay Petrojarl LLC for the upgrade, on completion of which the vessel will be redeployed at the Atlanta field in Brazil.

The project consists of the basic, detailed, construction and interface engineering; marine and process equipment procurement; fabrication; construction; corrosion protection/coating; transport and lifting operations; integration, mechanical completion, performance testing and commissioning activities. It also includes upgrades and modifications related to a marine, hull and life extension according to Class, conversion of the process systems (i.e. separation train and produced water topsides) and integration, and finally ensuring Brazilian compliance.

To achieve such a comprehensive upgrade DSR has formed partnerships with equipment supplier Frames BV and marine engineers Nevesbu BV. Frames is carrying out the design and fabrication of the new Topside Skids while Nevesbu is responsible for the marine and topside integration engineering.

The contract is being managed by DSC’s Offshore & Conversion task force team, and is to its knowledge the first EPC Redeployment Upgrade Contract to be carried out in Europe. By taking on responsibility for the hull, topside conversion and its integration, DSR was able to offer Teekay a turnkey package with regards to safety, quality, budget and delivery time.

This project represents a major step in the development of Damen Shiprepair and Conversion as a full service conversion group. As well as introducing valuable new partnerships, DSR has also used the contract to develop a professional project team tailored to the needs of the oil and gas industry. The sector is subject to extremely high HSEQ requirements and the Petrojarl I upgrade together with the experience gained from past projects such as the Gryphon A FPSO has established DSR as a serious contender for more such projects.

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

Dajin Forms Offshore Wind Alli

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

EnerMech Hires Former SLB Exec

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Eni Expands Asian Footprint wi

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Jasmund Substation’s Topside a

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine