Ensco delays DS-10 drillship

Houston’s Ensco agreed to an amendment with Samsung Heavy Industries (SHI) for the ENSCO DS-10 drillship construction contract that will see the delivery extended again until 31 March 2019.

Ensco said it may elect to take delivery of the drillship earlier upon giving SHI 75 days’ advance notice. Notwithstanding the extended delivery date, SHI agreed to complete construction of the drillship by 31 March 2017.

A payment of US$75 million of the approximately $309 million unpaid balance of the purchase price for the drillship has been deferred to 31 March 2019, or such earlier date as Ensco may elect to take delivery of the drillship.

The remaining $234 million of the purchase price is to be paid in January 2017.

Current News

Rhino Resources To Drill New Well Offshore Namibia

Rhino Resources To Drill New W

Fugro-Led BeWild Completes First Fully Remote Ecology Survey at OW Farm

Fugro-Led BeWild Completes Fir

TotalEnergies Secures Offshore Wind Concession in Germany

TotalEnergies Secures Offshore

MODEC and Terra Drone Renew FPSO Drone Inspection Partnership

MODEC and Terra Drone Renew FP

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine