BP has put its Murlach field in the U.K. North Sea into production, marking its sixth major project start-up in 2025.

The two-well subsea tieback at Murlach adds a peak net production of around 15,000 boed to the BP-operated Eastern Trough Area Project (ETAP) in the central North Sea, a hub that has been operating for 27 years.

The redevelopment included drilling two new wells, adding subsea equipment, reusing some existing kit, and making topside changes to the ETAP central processing facility.

The six projects BP started up in 2025 add around 150,000 barrels of oil equivalent per day (boed) combined peak net production, contributing to bp’s target to deliver an additional 250,000 boed combined peak net production by the end of 2027.

“Murlach is the sixth start-up for bp in 2025 and marks another important milestone in our plan to deliver 10 major upstream oil and gas projects by the end of 2027. These projects reflect Bp's strength in safely increasing production to supply energy to meet global demand, while maintaining a relentless focus on shareholder returns. They also highlight our focus on efficient delivery, with four starting up ahead of schedule,” said Ewan Drummond, BP’s senior vice president of projects.

“A key focus for bp in the North Sea is to identify opportunities that can be developed competitively using existing infrastructure to effectively manage established oil and gas hubs for the entirety of their lifespan. Murlach serves as another great example of this.

“It’s also testament to the skill and dedication of the bp team, our co-venturer NEO NEXT Energy, and supply chain colleagues,” added Doris Reiter, senior vice president of BP North Sea.

Categories: Safety & Security Drilling Hardware Natural Gas North Sea Industry News Activity Europe Production Oil and Gas Well Operations Workover FPSO

Related Stories

Vår Energi's Appraisal Well Confirms Barents Sea Oil Find

Major Offshore Renewables Emergency Exercise Tests Industry Response

DNO, Aker BP Strengthen Partnership to Fast-Track Kjøttkake Development

Current News

Norway Court Rules Against Oilfield Developments

Canada’s First Tidal Energy Array Authorized Using Adaptive Regulatory Framework

Seaturns Advances Full-Scale Wave Energy Trials in France

Archer Scoops $110M Oil Services Extension off UK

Subscribe for OE Digital E‑News