Equinor Restarts Hammerfest LNG Output

Tuesday, August 19, 2025

Norway's Equinors restarting its Hammerfest LNG plant following an unscheduled production outage and expects to begin filling its tanks with liquefied natural gas(LNG) on Tuesday afternoon local time, a spokesperson told Reuters.

Europe's largest export terminal for LNG shut down on Saturday due an overheating electrical transformer, the company has said.

The facility, also known as Melkoeya LNG, accounts for roughly 5% of all Norwegian gas exports.

The plant, which on August 4 ended a 15-week maintenance outage, has the capacity to deliver around 6.5 billion cubic metres of gas per year, enough to supply around 6.5 million European homes per day.

(Reuters)

Categories: Energy LNG People Industry News Production

Related Stories

GE Vernova Faces Revenue Hit After Offshore Wind Project Setbacks

Energean Forecasts Lower 2026 Gas Production

Beacon Offshore Starts Production at Zephyrus Field in US Gulf

Current News

Formosa 4 Offshore Wind Substation Enters Fabrication Phase

Mozambique and TotalEnergies Restart Stalled $20B LNG Project

Equinor Gets Permit to Drill North Sea Wildcat Well

Noble Completes $360M Sale of Five Jack-Ups to Borr Drilling

Subscribe for OE Digital E‑News