McDermott has executed its heaviest stacking lift at the Jebel Ali fabrication yard in Dubai as part of the BorWin6 980MW high-voltage, direct current (HVDC) project for TenneT.

The stacking of deck level one had a total weight of 1,962 metric tonnes (MT) and was conducted in a tandem lift operation involving six cranes.

This complex operation was executed by McDermott's lifting fabrication team, alongside construction support engineering, and its health, safety and environmental team. The lift was performed securely and ahead of schedule, according to McDermott.

Awarded in 2022, BorWin6 is a key part of McDermott's growing energy transition portfolio and represents the company's first project in the offshore wind market.

McDermott is delivering engineering, procurement, construction, installation and commissioning services, through a consortium with GEIRI / C-EPRI, for an HVDC offshore converter platform, located offshore Germany.

"Jebel Ali is unrivalled in its ability to deliver complex offshore structures. We are well positioned to continue driving execution excellence throughout the remainder of the construction phase, while maintaining the project's impeccable safety record,” said Rob Shaul, McDermott's Senior Vice President, Low Carbon Solutions.


Categories: Middle East Renewable Energy Industry News Activity Europe Offshore Wind HVDC

Related Stories

Norway Gives Go-Ahead to Two Consortia in Floating Wind Tender

Jan De Nul Unveils ‘Most Advanced’ Wind Farm Installation Simulator

IWS Fleet Fills Charter Gaps, Secures New CSOV Deals Into 2028

Current News

Seadrill Awarded Contract in the U.S. Gulf and Angola

Odyssey Marine Exploration Request for Offshore Mineral Lease Sale Advances

Technip Energies Gets On Board Thailand’s First CCS Project

Jan De Nul Wraps Up Cable Installation Job for TenneT’s DolWin Platform

Subscribe for OE Digital E‑News