First US-built WTIV Charybdis Launched

Eric Haun
Monday, April 15, 2024

The United States' first Jones Act-compliant offshore wind turbine installation vessel (WTIV), Charybdis, was launched into the water at the Seatrium AmFELS shipyard in Brownsville, Texas.

The 472-foot WTIV—the first and only to be constructed in the U.S.—is being built for Blue Ocean Energy Marine, a subsidiary of Dominion Energy, who announced the milestone on Monday. 

Welding of the ship's hull and commissioning of the vessel's four legs and related jacking system has been completed, Dominion said, and the vessel is expected to be completed and start sea trials by late 2024 or early 2025.

Charybdis is scheduled to be delivered in 2025 as a growing number of large-scale offshore wind developments ramp up in the U.S. Equipped with a 2,200mt Huisman leg encircling crane, the vessel is designed to handle turbine sizes of 12 megawatts (MW) or larger.

The $600-million-plus WTIV will first be deployed out of New London, Conn. to support the construction of Revolution Wind and Sunrise Wind offshore wind farms, both of which are being developed jointly by Ørsted and Eversource. 

The charter terms will allow the vessel to support the construction of Dominion's 2.6-gigawatt Coastal Virginia Offshore Wind (CVOW) project off the coast of Virginia Beach, which is expected to be completed in 2026.

It was announced today that the CVOW project received a final construction air permit from the Environmental Protection Agency (EPA), marking the final federal permit required to begin offshore construction. Offshore monopile installation for CVOW is expected to commence in May using DEME's installation vessel Orion.

Categories: Shipbuilding Offshore Vessels Activity North America Renewables Construction Vessel Offshore Wind

Related Stories

Dolphin Celebrates Multi-Year Contract Awards

He Dreiht Offshore Wind Farm: Final Turbine Installed

SLB, Equinor to Upgrade Vessel Under Multi-Year Well Stimulation Deal

Current News

Norway Approves Request to Delay Offshore Wind Farm License Application

TenneT Completes Drilling, Installation of Protective Conduits for Wind Farms

Alexandre de Gusmão FPSO Reaches Peak Production

Transocean Awarded $300 Million Contract for Ultra-Deepwater Drillship

Subscribe for OE Digital E‑News