Nexans Completes Cable Pull-Ins at Moray West Offshore Wind Farm

Monday, March 11, 2024

French subsea power cable maker Nexans has completed the offshore export cable pull-ins at 882 MW Moray West offshore wind farm in Scotland.

Nexans used its cable laying vessel Nexans Aurora to perform offshore export cable pull-ins for both offshore substation platforms (OSPs) as part of the offshore wind farm being developed by Ocean Winds, a joint venture of Engie and EDP Renewables.

The cable pull-in marks another key milestone for the project, as the OSP commissioning teams continue their work on the cable terminations.

The operations are part of the wider commissioning tasks, supported by Ocean Winds’ team onboard jack up vessel Leviathan with walk-to-work gangway to maximize safety and efficiency.

The next step will be the upcoming energization of the first circuit, Ocean Wind confirmed.

In December 2023, Boskalis installed the first offshore substation platform (OSP) for the project using its DP vessel Bokalift1. Two months later, DEME installed the first XXL monopile foundation as part of the project that will feature 60 Siemens Gamesa offshore wind turbines rated at over 14MW.

Under the power purchase agreement signed with the developers, Amazon will source 473MW of clean power from the wind farm, which is more than half of its capacity.


Categories: Offshore Energy Renewable Energy Subsea Industry News Activity Europe Subsea Cables Offshore Wind

Related Stories

France Lowers Renewable Goals, Backs Nuclear in New Law

NOV’s GustoMSC to Design Korea’s Wind Turbine Installation Vessel

Aquaterra Energy Gets Multi-Year Well Intervention Job off Spain

Current News

AF Offshore Secures North Sea Decom Job

Island Offshore’s Hybrid OECV Hits Water at Vard Yard in Romania (Video)

Jumbo Offshore Wraps Up Errea Wittu FPSO Mooring Pre-Lay in Guyana

Petronas Takes Operatorship of Oman’s Offshore Block 18

Subscribe for OE Digital E‑News