Wind industry service company FairWind has been awarded the turnkey pre-assembly contract for the offshore wind farms Vesterhav Nord and Syd at the Port of Esbjerg, Denmark.

FairWind will be responsible for the pre-assembly erection of 41 Siemens Gamesa’s SG 8.0-167 DD turbines. 

Each direct drive (DD) turbine will have a power generating capacity of 8.4MW. FairWind will start work in May 2023, and the wind farm is expected to be fully operational by the end of 2023.

The two wind farms, owned by Vattenfall, will have a combined capacity of 344MW. 

The project is expected to generate 1.57TWh of green power a year, sufficient to meet the energy needs of 380,000 households in Denmark.


Categories: Industry News Offshore Wind Activity

Related Stories

Semco Maritime Gets Iberdrola’s Baltic Hub Substations Service Job

Semco Maritime Gets Iberdrola’s Baltic Hub Substations Service Job

Ocean Winds Installs Substation for 496MW French Offshore Wind Farm

Ocean Winds Installs Substation for 496MW French Offshore Wind Farm

Osbit Opens New Offshore Wind Facility in Port of Blyth

Osbit Opens New Offshore Wind Facility in Port of Blyth

Current News

Bonaparte CCS Project Awarded Major Project Status

Borr Drilling Announces CEO Succession Plan

One Shelf Drilling Rig Up for New Job in India, Other for Disposal

Semco Maritime Gets Iberdrola’s Baltic Hub Substations Service Job

Subscribe for OE Digital E‑News

Offshore Engineer Magazine