Ørsted Taps Boskalis for Cable Installation at Borkum Riffgrund 3 and Gode Wind 3 Projects

Wednesday, November 10, 2021

Dutch marine contractor Boskalis will install inter-array cables at Ørsted's for the German Borkum Riffgrund 3 and Gode Wind 3 offshore wind farms. 

Boskalis said Wednesday that the contract would include the transport, installation, and burial of a combined total of 106 inter-array cables.

The company will use the Boka Ocean cable laying vessel.  Boskalis acquired the 136-meter-long vessel earlier this year and will equip it with a 4,000-ton turntable. Cable installation activities are scheduled for early 2024. Boskalis did not share the financial details of the award.

The Borkum Riffgrund 3 and Gode Wind 3 offshore wind farms will have a capacity of 900 MW and 242 MW respectively. 

Both wind farms are located off the northern coast of Germany in the North Sea. Combined, these two offshore wind farms are expected to deliver green renewable energy to approximately 1.2 million German households. The award of the contract is subject to a final investment decision by Ørsted.
 

Categories: Energy Vessels Subsea Offshore Wind Activity Europe Subsea Cables Cable Layers

Related Stories

GE Vernova Faces Revenue Hit After Offshore Wind Project Setbacks

Europeans Commit to Wind Energy Expansion Despite Trump Criticism

Norwind Offshore Takes Delivery of CSOV Newbuild from Vard

Current News

Formosa 4 Offshore Wind Substation Enters Fabrication Phase

Mozambique and TotalEnergies Restart Stalled $20B LNG Project

Equinor Gets Permit to Drill North Sea Wildcat Well

Noble Completes $360M Sale of Five Jack-Ups to Borr Drilling

Subscribe for OE Digital E‑News