Shell Expects Ida-hit Offshore Platform to Restart in November

Arathy S Nair
Friday, October 22, 2021

Shell said on Friday it expects an offshore transfer facility, which was shut due to damage from Hurricane Ida, to be operational in the first half of November, restarting production of a popular Gulf of Mexico crude grade earlier than expected.

The oil major was the hardest-hit producer from Ida, which tore through the Gulf of Mexico in August and removed 28 million barrels from the market.

Shell previously said it expected its West Delta-143 offshore facility, which transfers oil and gas from three major fields for processing at onshore terminals, to be offline for repairs until the end of 2021.

The fields are a key source of Mars sour crude, a grade prized by oil refiners in the United States and Asia. The disruptions hampered exports and raised crude prices, as buyers searched for substitutes.

Once the WD-143 facility is operational, the Mars oil pipeline expects to resume normal services as producers ramp up production, Shell said. The pipeline was expected to be offline until early 2022.

About 200,000 to 250,000 barrels per day of oil supply from the Gulf of Mexico was expected to be affected due to damage to the facilities from Ida, Research firm Rystad Energy had said. 

(Reporting by Arathy S Nair in Bengaluru; Editing by Shinjini Ganguli and Shounak Dasgupta)

Categories: Deepwater Production Gulf of Mexico Offshore

Related Stories

DEME Set for Monopiles, Cables Installation Job at Polish Offshore Wind Farm

Australian Union Members Back Pluto LNG 2 Strike

CNOOC Puts New South China Sea Development Into Production Mode

Current News

Jumbo Scoops Two Offshore Wind Contracts

Wood Nets Long-Term Maintenance Contract for Rio Grande LNG Facility

TechnipFMC to Supply Subsea Systems for Chevron’s Gas Project off Australia

Shell Picks Valaris Drillship for Work Offshore Brazil

Subscribe for OE Digital E‑News