BP Brings Online Matapal Project Offshore Trinidad and Tobago

Monday, September 20, 2021

BP's Matapal project offshore Trinidad and Tobago has achieved first gas, BP Trinidad and Tobago said Monday.

Matapal is BPTT’s second subsea development and it consists of three wells, which tie back into the existing Juniper platform via two 9 km flexible flowlines.

Sitting in a water depth of 163 meters, Matapal is located 80 kilometers off the south-east coast of Trinidad and about 8 kilometers east of Juniper.

Matapal will deliver gas into the Trinidad gas market from resources discovered by the Savannah exploration well, drilled in 2017. The initial production from this development is expected to be in the range of 250-350 million standard cubic feet per day (mmscfd), once all wells are fully ramped up.  

Construction work on Matapal started in 2019. The project called for modification to the existing Juniper platform as well as the construction and installation of new subsea equipment. 

Importantly, the majority of fabrication work required to adapt the Juniper platform for new production was completed locally. Hydrocarbons from Matapal will be transported to the Juniper platform

BPTT has 15 offshore production platforms in Trinidad and Tobago, and is the country’s largest hydrocarbon producer, accounting for some 55% of the nation’s gas production.

Categories: Energy Caribbean Activity Production

Related Stories

Kuwait Sees 70% Oil Output Recovery within Two Months of Hormuz Reopening

Indonesia Targets Higher Oil and Gas Output in 2027

Seven US States Sue Fed. Government, TotalEnergies After Cancelling Offshore Wind Lease

Current News

Norway Vote on Subsidies Review Casts Doubt on Floating Wind Project

Global Offshore Wind Capacity Expected to Quadruple by End of 2035

Al-Designed CTV Saves 100,000 Liters of Fuel, 258 Tons of CO2 a Year

BP Merges Businesses Into Upstream and Downstream Divisions

Subscribe for OE Digital E‑News