PHOTO: First Moray East Offshore Substation Installed

Tuesday, August 11, 2020

The first of three offshore substations has been installed at the Moray East Offshore wind farm site in the UK, Moray Offshore Windfarm (East) Ltd said Monday.

The 950MW wind farm is being developed by Moray Offshore Windfarm East Ltd (MOWEL), which is a joint venture company owned by Diamond Green Limited (33.4%), Ocean Winds (56.6%) and CTG (10%).

The modular offshore substation platform topside which contains all of the electrical infrastructure to transmit the electricity generated by the offshore wind turbines, was installed on top of the three-legged jacket structure, which was previously fastened on the sea-bed. 

The offshore substation platform topside was designed and built by Siemens. DEME delivered and installed the jacket and installed the topside on the jacket.

The topside was installed using the Seajack’s Jack-Up Vessel ‘Scylla’ having previously loaded it onboard from Global Energy’s facility at Nigg.



The 1200 tonne topside contains all the essential electrical equipment including transformers and switchgear to transmit the electricity generated by roughly one-third of the 100 offshore wind turbines and increase its voltage from 66kV to 220kV so that it can be delivered through the export cable to shore with maximum efficiency and minimum losses.

The lifting operation required the precision mating of the 30mx28m topside with stabbing pins on the jacket within a tolerance of only 30mm.

In total, three offshore substations will be installed within the next couple of weeks-

The electricity will come ashore at Inverboyndie, and will then be routed via underground cables to the Moray East substation at New Deer from where the electricity is fed into the National Grid.

Project Director Marcel Sunier said: “The safe installation of our first offshore electrical infrastructure is a very significant milestone.  A 1200 tonne precision-lift is a major undertaking in any situation – and even more so in the challenging  waters of the Moray Firth, and I congratulate all those involved and I am looking forward to see the other two substation platforms being installed shortly.”

Categories: Energy Activity Europe Renewables Offshore Wind

Related Stories

New England Offshore Wind Auction Draws Multiple Bidders

Nexans Secures First Call-Off Under TenneT’s Offshore Wind Grid Deal

RWE Joins Forces with Spanish Port to Create Floating Wind Hub

Current News

Baker Hughes: US Drillers Cut Oil and Gas Rigs for Second Week In A Row

Seaway7 Gets Baltica 2 Offshore Wind Job

First Gas Export to Denmark from Tyra II Expected Today

Vattenfall to Take Part in IJmuiden Ver Offshore Wind Tender in Netherlands

Subscribe for OE Digital E‑News