Petronas PFLNG1 construction at 95%

OE Staff
Wednesday, December 30, 2015

The Petronas floating LNG1 (PFLNG1) has reached a 95% overall progress in its construction and will come onstream in 2016, the company said.

In late September, Petronas began lifting the first topside module for its PFLNG1 facility at the Daewoo Shipbuilding and Marine Engineering (DSME) shipyard in Okpo, South Korea. 

The topside module lifting marks another major construction milestone for the facility, as it signifies the near completion of the PFLNG1, which will be the world’s first floating LNG facility in operation.

Once the construction and installation phases are completed in 2015, PFLNG1 will be moored in Kanowit field, which is about 180km offshore Sarawak, Malaysia.

Read more:

Technip wins PFLNG1 tieback work

Categories: Natural Gas Construction FLNG Asia LNG

Related Stories

Noble Completes $360M Sale of Five Jack-Ups to Borr Drilling

RWE Divests Swedish Wind Portfolio in Deal with Nordic Player Aneo

Wes Heiskell Takes Position at Paradigm Drilling Services

Current News

Shell Sells 20% Stake in Offshore Orca Project to Kuwaiti Foreign Petroleum Exploration Company

Seatrium Wraps Up AmFELS Yard Sale

Strategic Marine Delivers CTV for Taiwan’s Offshore Wind Sector

Eni Enlists Shearwater for 3D Seismic Survey in Timor Sea

Subscribe for OE Digital E‑News