Petronas PFLNG1 construction at 95%

OE Staff
Wednesday, December 30, 2015

The Petronas floating LNG1 (PFLNG1) has reached a 95% overall progress in its construction and will come onstream in 2016, the company said.

In late September, Petronas began lifting the first topside module for its PFLNG1 facility at the Daewoo Shipbuilding and Marine Engineering (DSME) shipyard in Okpo, South Korea. 

The topside module lifting marks another major construction milestone for the facility, as it signifies the near completion of the PFLNG1, which will be the world’s first floating LNG facility in operation.

Once the construction and installation phases are completed in 2015, PFLNG1 will be moored in Kanowit field, which is about 180km offshore Sarawak, Malaysia.

Read more:

Technip wins PFLNG1 tieback work

Categories: Natural Gas Construction FLNG Asia LNG

Related Stories

Deepsea Bollsta Rig Gets New Name as Odfjell Drilling Takes Ownership

Dong Fang Offshore Picks Westcon for New CLV Delivery

Eni Makes Significant Gas Discovery Offshore Indonesia

Current News

2025: Fascinated with Subsea Discovery

Petrobras strike-hit P-40 Platform shut down after gas leak: union

Aker BP Extends Scarabeo 8 Contract for Offshore Drilling in Norway into 2028

Poland Allocates 3.4 GW Capacity in Offshore Wind Auction

Subscribe for OE Digital E‑News