CMC Installed on Ocean Blackhawk Drillship

Published


ST Engineering Halter Marine and Offshore (STEHMO) installed a NOV crown mounted compensator (CMC) on Diamond Offshore’s Ocean Blackhawk drillship.

The 215-metric-ton passive heave compensator was fully assembled and lifted on the top of the derrick on May 22, 2019. Carol Crane Rigging & Lifting Technology and Mammoet supported STEHMO with completing the engineered lift. STEHMO also cleaned and painted tanks, lifeboats and the exterior hull above the waterline.

Before the lift, shipyard cranes removed the existing A frame from atop the derrick and supported the NOV with all the modifications required to suit the new crown mounted compensator. In addition to the CMC installation, STEHMO, formerly known as VT Marine, fabricated and installed an HPU platform along with other minor changes to the existing pipe systems.

“We take great pride in offering the facilities, along with the skilled professionals necessary, to accomplish a project of this scale,” said Nian Hua Lim, President and CEO, STEHMO.

Ocean Blackhawk is a Gusto P10,000 DW design drillship that entered service in 2014.

Current News

AF Offshore Secures North Sea Decom Job

AF Offshore Secures North Sea

Island Offshore’s Hybrid OECV Hits Water at Vard Yard in Romania (Video)

Island Offshore’s Hybrid OECV

Jumbo Offshore Wraps Up Errea Wittu FPSO Mooring Pre-Lay in Guyana

Jumbo Offshore Wraps Up Errea

Petronas Takes Operatorship of Oman’s Offshore Block 18

Petronas Takes Operatorship of

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine