CMC Installed on Ocean Blackhawk Drillship

Published


ST Engineering Halter Marine and Offshore (STEHMO) installed a NOV crown mounted compensator (CMC) on Diamond Offshore’s Ocean Blackhawk drillship.

The 215-metric-ton passive heave compensator was fully assembled and lifted on the top of the derrick on May 22, 2019. Carol Crane Rigging & Lifting Technology and Mammoet supported STEHMO with completing the engineered lift. STEHMO also cleaned and painted tanks, lifeboats and the exterior hull above the waterline.

Before the lift, shipyard cranes removed the existing A frame from atop the derrick and supported the NOV with all the modifications required to suit the new crown mounted compensator. In addition to the CMC installation, STEHMO, formerly known as VT Marine, fabricated and installed an HPU platform along with other minor changes to the existing pipe systems.

“We take great pride in offering the facilities, along with the skilled professionals necessary, to accomplish a project of this scale,” said Nian Hua Lim, President and CEO, STEHMO.

Ocean Blackhawk is a Gusto P10,000 DW design drillship that entered service in 2014.

Current News

France Calls Draft Law on Oil Exploration in Overseas Territories

France Calls Draft Law on Oil

Formosa 4 Offshore Wind Substation Enters Fabrication Phase

Formosa 4 Offshore Wind Substa

Mozambique and TotalEnergies Restart Stalled $20B LNG Project

Mozambique and TotalEnergies R

Equinor Gets Permit to Drill North Sea Wildcat Well

Equinor Gets Permit to Drill N

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine