Albatros Topside Installed

The topside for the Albatros substation has been installed in the German North Sea. (Photo: EnBW)
The topside for the Albatros substation has been installed in the German North Sea. (Photo: EnBW)

The topside of the offshore substation at the Albatros wind farm offshore Germany was installed Tuesday evening, developer EnBW said.

The heavy-lift jack-up vessel (HLJV) Pacific Ospray had loaded the topside in Rotterda, and once in the construction area, the HLJV Innovation lifted the topside on the foundation (monopile and transition piece) that had already been installed. 

The Pacific Ospray will be jacked up and remain next to substation until outstanding coating and welding work is completed.

Afterwards, the jack-up vessel Seafox2 will come to commission the offshore substation.

Current News

ScottishPower, Oasis Marine Study Proves Feasibility of Offshore Charging

ScottishPower, Oasis Marine St

Africa Energy Aims to Start Production in South Africa by 2033

Africa Energy Aims to Start Pr

Repsol Hires Halliburton for Well Lifecycle Optimization of North Sea Assets

Repsol Hires Halliburton for W

Aquaterra Energy to Deliver Well Services Work for North Sea CCS Project

Aquaterra Energy to Deliver We

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine