AMEC was awarded a two-year contract extension from BG Group to continue to provide engineering, procurement, construction, commissioning, and project management support for all of BG Group’s facilities in the central North Sea.

The contract is valued at about US $170 million and is scheduled to run through to December 2015. The extension follows on from the original three-year contract award in 2011. 

Under the original contract AMEC completed severalprojects including two subsea tie backs from the Gaupe, North West Seymour wells, a subsequent major topside modification of the Armada platform, topside modifications on the North Everest platform, and a subsea tie back as part of the Everest East expansion. 

AMEC has having achieved 7 million man hours without a Lost Time Incident (LTI) since the project began. The company supplies consultancy, engineering and project management services to the oil and gas, mining, clean energy, environment and infrastructure markets. 

Current News

DeepOcean Awarded IMR Contract Extension by Equinor

DeepOcean Awarded IMR Contract

BOEM Initiates Process for Potential Mineral Lease Sale Offshore Virginia

BOEM Initiates Process for Pot

Jumbo Scoops Two Offshore Wind Contracts

Jumbo Scoops Two Offshore Wind

Wood Nets Long-Term Maintenance Contract for Rio Grande LNG Facility

Wood Nets Long-Term Maintenanc

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine