Deutsche Bucht Offshore Wind Substation Nears Completion

Published

 Photo: Damen Shiprepair Vlissingen
Photo: Damen Shiprepair Vlissingen

Ten months after the final assembly of the offshore substation (OSS) for the new Deutsche Bucht offshore wind farm started at Damen Shiprepair Vlissingen (DSV), the substation topside has now been moved outside the construction hall so that further outfitting can take place.

The Deutsche Bucht offshore wind farm, owned by Northland Power, will have 33 turbines, situated 95 kilometers northwest of Germany’s Borkum Island, in the North Sea. The wind farm will have a total capacity of 269 MW.

Van Oord is managing the overall Balance of Plant scope, including the OSS project, with the joint venture Iemants-Eiffage contracted for the engineering, procurement, construction and installation of the substation topside and jacket. Together with Damen Schelde Naval Shipbuilding, DSV is managing the yard facilities and supporting the OSS works by providing welding and painting services.

Offshore installation is planned in the first half of 2019.

Current News

France Calls Draft Law on Oil Exploration in Overseas Territories

France Calls Draft Law on Oil

Formosa 4 Offshore Wind Substation Enters Fabrication Phase

Formosa 4 Offshore Wind Substa

Mozambique and TotalEnergies Restart Stalled $20B LNG Project

Mozambique and TotalEnergies R

Equinor Gets Permit to Drill North Sea Wildcat Well

Equinor Gets Permit to Drill N

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine