First Turbine Stands Tall at Vietnam’s 128MW Offshore Wind Farm

Wednesday, September 16, 2026

Chinese supplier Envision Energy has installed the first turbine at the 128 MW Vinh Long nearshore wind project in Vietnam, marking the first turbine installation for its first international offshore wind project.

The project, developed by REE Group, will comprise 16 Envision EN-226/8.X MW turbines, with full-scale installation now underway.

The first turbine was installed in less than seven days, with the second in under five days, while the first equipment was delivered five months after the contract was signed.

Installation has continued despite heavy rainfall, strong winds and typhoons, as well as limited installation resources.

Envision said the EN-226 features a lighter design intended to simplify installation and maintenance in nearshore conditions.

All 16 turbines are expected to be installed in rapid succession.

Categories: Technology Renewable Energy Industry News Activity Asia Offshore Wind

Related Stories

RWE, Masdar Plan German Offshore Wind Partnership

Ørsted Gets Favorable Tax Opinion on Two UK Wind Farms

GONDAN Launches Its Largest-Ever Vessel Built for Østensjø Rederi

Current News

EU Set to Restart Scrutiny of Subsea 7-Saipem Combination

First Turbine Stands Tall at Vietnam’s 128MW Offshore Wind Farm

Equinor Gets Clearance for Drilling Ops in North Sea

PTTEP Gets Thai Approval for Offshore Stake Transfer to Valeura Energy

Subscribe for OE Digital E‑News