Jasmund Substation Nears Baltic Sea Installation After Topside and Jacket Load-Out

Tuesday, November 18, 2025

The Jasmund offshore substation project for German grid operator 50Hertz, being delivered by HIS consortium, has reached a key milestone with the load-out of both its topside and jacket, marking a major step toward offshore installation in the Baltic Sea.

The topside, built at HSM Offshore Energy’s Stormpolder yard in the Netherlands, measures 48 meters by 33 meters, stands 17.5 meters high and weighs about 4,500 tonnes. The matching 4,500-tonne jacket, rising 72 meters, was manufactured at the Smulders yard in Vlissingen.

Both structures were transferred onto barges following detailed planning to ensure safe load distribution, structural stability and transport readiness. A customized grillage system was designed to support the substation during the transfer.

The project is being executed by the HSI consortium – HSM Offshore Energy, Smulders and Iv – which holds the full EPCIC scope covering engineering, procurement, construction, installation and commissioning. OSS Jasmund is the first of three offshore substations the consortium is delivering for 50Hertz.

Once operational, the Jasmund substation will have a capacity of 300 MW, supplying renewable electricity to around 260,000 households. It will serve as the grid connection point for the Windanker offshore wind farm, located northeast of Germany’s island of Rügen.

Earlier this year, the HSI joint venture completed the rollout of the topside and lifted transformers at the Stormpolder yard, marking the first substation platform and jacket to be delivered under the partnership.


Categories: Technology Offshore Offshore Energy Renewable Energy Industry News Activity Europe Offshore Wind Substations

Related Stories

Formosa 4 Offshore Wind Substation Enters Fabrication Phase

Europe Turns to Offshore Wind to Curb Dependence on US Gas

European North Sea Investment Pact to Mobilize $1.17T for Offshore Wind

Current News

More to Consider than CO2 in CCS Leakage Risks

France Calls Draft Law on Oil Exploration in Overseas Territories

Formosa 4 Offshore Wind Substation Enters Fabrication Phase

Mozambique and TotalEnergies Restart Stalled $20B LNG Project

Subscribe for OE Digital E‑News