Norway's Hammerfest LNG Shuts Down

Monday, August 18, 2025

Norway's Hammerfest LNG terminal shut its production of liquefied natural gas during the weekend due an overheating electrical transformer, a spokesperson for operator Equinor EQNR.OL said on Monday.

The facility, also known as Melkoeya LNG, accounts for roughly 5% of all Norwegian gas exports.

The outage at Europe's largest LNG export facility began on Saturday afternoon local time and is expected to end at 2100 GMT on Monday, according to a regulatory statement posted by Equinor on the Gassco gas system website.

The plant, which on August 4 ended a 15-week maintenance outage, has the capacity to deliver around 6.5 billion cubic metres of gas per year, enough to supply around 6.5 million European homes per day.

(Reuters)

Categories: Energy LNG Industry News Norway

Related Stories

BOTAS Inks 10-Year LNG Supply Deals with SEFE and Eni

Eni Starts Up Phase 2 of Congo LNG Ahead of Schedule

Semco Maritime to Work on Floatel Endurance Rig Optimization

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Subscribe for OE Digital E‑News