Argeo Concludes Work for TotalEnergies Offshore Namibia

Tuesday, March 18, 2025
Argeo Venture vessel (Credit: Argeo)

Norwegian offshore services company Argeo has completed deepwater work at TotalEnergies’ Venus project, offshore Namibia, taking somewhat longer than expected.

Argeo mobilized its Argeo Venture vessel for the job, which is now demobilizing in Walvis Bay, scheduled to be completed on March 23, 2025.

The work was conducted as part of the $39 million contract Argeo secured with TotalEnergies back in April 2024.

Accoridng to Argeo, the vessel started work in Namibia on May 20, 2024 after transiting from Norway.

The project has taken somewhat longer than initially estimated due to an unexpectedly long yard-stay and poorer weather conditions than expected.

In total, Argeo Venture spent close to 10 months on project, delivering over 7000-line km of AUV geophysical data and close to 200 geotechnical samples in water depth exceeding 3000 meters.

“The contract and work program reaffirm our capability to deliver top-tier deep-water services and demonstrated our ability to execute integrated geophysical and geotechnical projects, where the geotechnical component is derived from geophysical data that is efficiently processed on board,” Argeo said in a statement.

To remind, in December 2024, Argeo signed a five-year frame agreement with TotalEnergies for offshore site investigation services, which could be extended for additional two years.


Categories: Vessels Offshore Energy Geoscience Subsea Industry News Activity Africa AUV Oil and Gas

Related Stories

Industry Partners Deliver Largest Unified OBN Dataset in Norwegian North Sea

Industry Partners Deliver Largest Unified OBN Dataset in Norwegian North Sea

Fugro Gets On Board Ireland’s Offshore Grid Development Project

Fugro Gets On Board Ireland’s Offshore Grid Development Project

PXGEO Appoints Head of Strategy and Transformation

PXGEO Appoints Head of Strategy and Transformation

Current News

SLB Narrowly Beats Quarterly Profit Estimates

Vard Books Construction Order for CSOV Pair

ABL to Deliver Grid Works for 600MW French Offshore Wind Farm

Cadeler Adds Wind Keeper WTIV to Fleet, Locking in Long-Term Vestas Deal

Subscribe for OE Digital E‑News

Offshore Engineer Magazine