Orsted, PGE Greenlight Poland Offshore Wind Farm

Wednesday, January 29, 2025

Poland's PGE and Denmark's Orsted have taken the final decision to build Baltica 2, a 1.5-gigawatt offshore wind farm on Poland's Northwestern coast, the companies said on Wednesday.

Both companies will own 50% of the farm which is expected to be fully commissioned in 2027, a joint statement read.

"All major component and vessel contracts for Baltica 2 have been signed," the statement said, adding that most of the project's capital expenditure was locked in.

Orsted and Poland's largest power group, state-controlled PGE, in 2021 decided to develop two offshore wind farms totalling 2.5 Gigawatts.
PGE has said it expects power from Baltic Sea wind farms to account for 40% of its electricity generation in 2040.

(Reuters)

Categories: Technology Offshore Energy Industry News Offshore Wind Poland

Related Stories

Taiwan's 1GW Hai Long Offshore Wind Farm Brings All Turbines Online

Gennaker Offshore Substations Depart for Baltic Sea Installation (Video)

Lamprell Picks IMI for Offshore Platforms and Jackets Fabrication

Current News

Incat Crowther to Build Fourth Fast Support Intervention Vessel

Equinor Exercises Two Well Option for Deepsea Atlantic Rig

Taiwan's 1GW Hai Long Offshore Wind Farm Brings All Turbines Online

ACCIONA Lands 2GW Offshore Wind Grid Deal in Australia

Subscribe for OE Digital E‑News