Poland's PGE and Denmark's Orsted have taken the final decision to build Baltica 2, a 1.5-gigawatt offshore wind farm on Poland's Northwestern coast, the companies said on Wednesday.

Both companies will own 50% of the farm which is expected to be fully commissioned in 2027, a joint statement read.

"All major component and vessel contracts for Baltica 2 have been signed," the statement said, adding that most of the project's capital expenditure was locked in.

Orsted and Poland's largest power group, state-controlled PGE, in 2021 decided to develop two offshore wind farms totalling 2.5 Gigawatts.
PGE has said it expects power from Baltic Sea wind farms to account for 40% of its electricity generation in 2040.

(Reuters)

Categories: Technology Offshore Energy Industry News Offshore Wind Poland

Related Stories

Coastal Virginia Offshore Project Costs Increases to $11.5b

Cadeler Lines Up Offshore Wind Foundation Installation Job

European North Sea Investment Pact to Mobilize $1.17T for Offshore Wind

Current News

Coastal Virginia Offshore Project Costs Increases to $11.5b

Equinor Extends Seadrill Drillship’s Stay off Brazil

MODEC Partners with Eld Energy, Delta to Advance FPSO Decarbonization

Conrad, Empyrean Agree Settlement Framework Over Duyung PSC Interests

Subscribe for OE Digital E‑News