Mammoet to Marshal XL Monopile Foundations for RWE’s Offshore Wind Farms

Monday, November 18, 2024
(Credit: Mammoet)

Mammoet has signed a contract with Buss Ports to marshal over 100 XL monopile foundations for RWE’s offshore wind farms Nordseecluster A and Thor.

The Nordseecluster, with a planned capacity of up to 1.6 GW, is one of the largest offshore wind energy projects in Germany and will be constructed in two phases (A & B).

Thor, with a planned capacity of more than 1 GW to power more than one million homes, is Denmark’s largest to date.

Mammoet will manage the phased load-in, temporary storage and load-out of 116 XXL monopiles for both wind farm projects at Buss Terminal Eemshaven in the Netherlands.

The largest foundations will weigh around 1,700 tonnes and measure 96 meters in length.

The monopiles will be offloaded onto the quay using a RoRo linkspan ramp and transported using Self-Propelled Modular Transporters (SPMTs) fitted with saddles.

The SPMT trailers will then drive the monopiles onto storage dunes, ready to be called off and shipped to the wind farms located in the German and Danish waters of the North Sea.

“This is a complex marshalling operation, with large components for both farms needing to be moved and managed on a single site.

“Combining our specialist heavy transport equipment with our engineering experience of monopile handling, we are delighted to support the development of these significant offshore wind projects concurrently,” said Wouter Santen, Project Manager at Mammoet.

“Mammoet has a proven track record for managing the movement of monopiles safely and efficiently. Having them by our side during the planning stage has been invaluable. We look forward to working with them as we move into the assembly phase,” added Marc Wegman, Managing Director of Buss Terminal Eemshaven.

Categories: Renewable Energy Industry News Activity Europe Offshore Wind

Related Stories

Equinor Takes $955M Impairment Hit on US Offshore Wind Farm

Equinor Takes $955M Impairment Hit on US Offshore Wind Farm

Siemens Gamesa Lines Up 63-Turbine Order for German Offshore Wind Farm

Siemens Gamesa Lines Up 63-Turbine Order for German Offshore Wind Farm

Cierco Energy and MPS Team Up for Celtic Sea Floating Wind Demo

Cierco Energy and MPS Team Up for Celtic Sea Floating Wind Demo

Current News

TotalEnergies Starts Up Two Subsea Tie-Back Projects in Angola

Dong Fang Offshore Orders Huisman Cable Lay System

Expro Launches Advanced BRUTE Tool for Deepwater Wells

Lamprell Picks Ventherm’s Robotic Solution for Offshore Wind Transition Pieces

Subscribe for OE Digital E‑News

Offshore Engineer Magazine