Havfram Gets Turbine Installation Job at German Offshore Wind Farm

Wednesday, September 25, 2024

Havfram has signed a contract with Luxcara, an independent German asset manager specialized in clean energy infrastructure projects, for the transport and installation support of wind turbines for the Waterkant offshore wind farm in the German North Sea.

The agreement covers the vessel charter for transport and installation of 16 of the foreseen 18.5 MW turbines.

Havfram will execute the works during the spring of 2028, using one of its advanced Wind Turbine Installation Vessels (WTIVs), currently under construction.

Waterkant will be built approximately 90 km off the island of Borkum and have a capacity of approximately 270 MW.

"We are honored to contribute to Germany's renewable energy goals by supporting Luxcara with the Waterkant project. This agreement not only expands our growing client portfolio, but also strengthens our contract backlog. With our two state-of-the-art WTIVs that are due to be delivered second half of 2025, Havfram is perfectly equipped to meet the challenges of the offshore wind industry,” said Even Larsen, CEO at Havfram Wind. He added: “

Categories: Vessels Renewable Energy Industry News Activity Europe Offshore Wind

Related Stories

EEW, CS Wind Deliver First Offshore Wind Monopiles for Vattenfall’s Nordlicht I

Akita Offshore Wind Build Progresses as JERA Defies Cost Pressures

France Lowers Renewable Goals, Backs Nuclear in New Law

Current News

Ndungu Full-Field Starts Up Offshore Angola

Norway's 2025 Oil Output Climbs to Highest Level Since 2009

AKOFS Offshore Inks New Vessel Deal with Petrobras

UK Trade Body Challenges Government View on North Sea Gas Decline

Subscribe for OE Digital E‑News