Minesto Generates First Power with 1.2MW Tidal Energy Kite

Friday, February 9, 2024

Swedish marine energy company Minesto has reached a key milestone with the delivery of first electricity to Faroe Island’s grid from its 1.2MW utility-scale Dragon 12 tidal energy device.

In the early morning of February 9, the Dragon 12 device was successfully commissioned and started producing power ‘at satisfactory levels’ in its first phase of operation, Minesto informed.

The 12-meter wide and 28-ton heavy subsea kite, anchored with a tether to the seabed, is steered in an eight-shaped flight trajectory powered by the tidal flow.

“This is a big day for Minesto. We have reached the most significant milestone in the history of the company by producing electricity to the grid with our mega-watt scale powerplant. We are both proud and happy and more than ever look forward to the journey ahead,” said Martin Edlund, CEO of Minesto.

Dragon 12 is a 10-times scale-up from the existing 100 kW Dragon 4, designed for buildout of large-scale commercial tidal energy farms.


Categories: Technology Offshore Energy Renewable Energy Subsea Industry News Activity Europe Tidal Energy

Related Stories

SLB to Provide Engineering Services for Norway's Havstjerne CCS Project

Viridien Progresses Hybrid Multi-Client Survey Offshore Malaysia

MacGregor Advances Floating-to-Floating Transfer and LCO2 Systems

Current News

Chevron, ENI, Geopark Signs Energy Agreements in Venezuela

Ian Tyler Appointed bp Chair

Ørsted Hosts Ceremony for Greater Changhua 2b and 4 Completion

Hornbeck and Helix Complete Merger

Subscribe for OE Digital E‑News