Delfin Asks for Another Year to Build Louisiana Floating LNG Project

Scott DiSavino
Thursday, July 1, 2021

U.S. liquefied natural gas (LNG) developer Delfin LNG asked federal energy regulators for a third extension until September 2022 to bring into service the onshore facilities of its proposed floating LNG export plant off the coast of Louisiana.

The U.S. Federal Energy Regulatory Commission (FERC) in September 2017 authorized Delfin to build its project by September 2019.

In June 2019, Delfin asked FERC for an extension to finish the project until March 2023. FERC, however, only gave Delfin a one-year extension until September 2020.

In June 2020, Delfin asked and received another one-year extension from FERC to finish the project by September 2021.

In asking for this third extension, Delfin said global "economic conditions are recovering from the COVID-19 pandemic and the spot and short-term markets for LNG have significantly improved ... which will support the company to enter into long-term LNG offtake contracts."

Delfin is one of more than a dozen North American LNG export projects that have repeatedly pushed back decisions to start construction due primarily to a lack of customers signing long-term deals needed to finance the multibillion-dollar facilities.

Delfin said in its FERC filing it "is confident that it will secure commercialization in the coming year."

Delfin's project would use existing offshore pipelines to supply gas to up to four vessels that could produce up to 13 million tonnes per annum (MTPA) of LNG or 1.7 billion cubic feet per day (bcfd) of natural gas.

(Reporting by Scott DiSavino; Editing by Mark Potter)

Categories: Offshore Energy LNG Vessels Industry News Activity Production North America FLNG

Related Stories

ABB’s Streamlined DP2 System Passes Sea Trials on DEME’s Norse Wind WTIV

US Judge Overturns Trump’s Freeze on Wind Energy Permits

CNOOC Puts New South China Sea Development Into Production Mode

Current News

Thistle Wind Partners Submits Plans for Bowdun Offshore Wind Farm

Seatrium Gets Repeat Order from IMI for Arabia 4 Jack-up Rig

Sea Lion Oil Project in Falkland Islands Gets Green Light

ABB’s Streamlined DP2 System Passes Sea Trials on DEME’s Norse Wind WTIV

Subscribe for OE Digital E‑News