Rovco, CWind Wrap First Phase of East Anglia ONE Subsea Inspection Works

Wednesday, November 4, 2020

Rovco, a UK-based provider of ROV and hydrographic services has completed the first stage of its long-term contract awarded by CWind for its annual subsea balance of plant (BOP) and cable inspection works at East Anglia ONE offshore windfarm in the UK. 

The East Anglia ONE offshore wind farm, with the capacity to produce 714MW of electricity, first delivered power to the UK grid in early September 2019. All 102 turbines are now installed and the wind farm was fully commissioned in July 2020

CWind, part of the Global Marine Group, was awarded a multi-year framework from ScottishPower Renewables and Macquarie's Green Investment Group to manage the subsea inspection services, including subsea maintenance, surveys and corrective maintenance planning, as well as pre-engineering studies at the offshore wind farm.

Rovco, led by CWind, began work in July 2020 – using a combination of DPII SOV with its Seaeye Leopard Work-Class ROV onboard, to carry out inspection works on nominated subsea structures and a Survey Vessel solution for multibeam and side scan work along the Array and Export Cable routes. This work assisted in notifying the condition of the operational windfarm to allow informed maintenance planning as required based on the results of the surveys, Rovco said.

Categories: Vehicle News Subsea Industry News Offshore Wind Activity Europe ROV

Related Stories

50Hertz, Skyborn Ink Deal for Gennaker Offshore Converter Platforms

TGS Bags Second OBN Contract in Europe

SMD Clears Electric Work-Class ROV for Deployment with Jan de Nul

Current News

Formosa 4 Offshore Wind Substation Enters Fabrication Phase

Mozambique and TotalEnergies Restart Stalled $20B LNG Project

Equinor Gets Permit to Drill North Sea Wildcat Well

Noble Completes $360M Sale of Five Jack-Ups to Borr Drilling

Subscribe for OE Digital E‑News