Following the arrival of Van Oord's Svanen heavy-lift vessel at the Kriegers Flak Offshore Wind Farm location offshore Denmark earlier this week, the first foundation has now been placed on the seabed, Vattenfall, the operator of what will be Denmark's largest offshore wind farm, said Friday.

"The foundation represents the first visual offshore part of the wind farm itself. It’s a milestone in the development of this great project and Vattenfall’s journey towards enabling fossil-free living”, says Catrin Jung, Head of Offshore Wind, Vattenfall.

On the foundations, 72 turbines will be mounted to create Denmark’s largest offshore wind farm with a capacity to cover the annual electricity consumption of approximately 600,000 Danish households.

Installation of the foundations is expected to run into the autumn this year with the installation of turbines starting in 2021. 

"Despite restrictions following the COVID-19 pandemic, the development of Kriegers Flak is on schedule to be in full operation by the end of 2021, at the latest," Vattenfall said.

Kriegers Flak is the latest and largest of Vattenfall’s recent offshore projects in Denmark. The others being Horns Rev 3, which was inaugurated last year, and Vesterhav Syd & Nord, which are scheduled to be in full operation by the end of 2023, at latest.


Categories: Installation Energy Renewable Energy Subsea Industry News Offshore Wind Activity

Related Stories

Cadeler’s WTIV Newbuild En Route to Europe for Maiden Offshore Wind Job

UK’s GEB Plans Major Renewables Expansion Through 2030

Windcat Orders Next-Gen Multi-Purpose Offshore Support Vessel

Current News

Texas LNG Signs 20-Year Offtake Deal with Macquarie

Petrobras and Shell Raise Stakes in Brazil’s Atapu and Mero Pre-Salt Fields

Chevron's Gorgon LNG Project Gets $2B Investment Go-Ahead

Van Oord Completes Monopile Installation at Windanker

Subscribe for OE Digital E‑News