DEME Hits Halfway Mark with Borssele Wind Farm Installation

OE Staff
Friday, April 10, 2020

Offshore installation company DEME Offshore has said made strong progress with the installation of the foundations for offshore wind turbines at Ørsted’sBorssele 1 & 2 Offshore Wind Farm in the Dutch North Sea, reaching the halfway mark. 

Having started construction works with offshore installation vessel ‘Innovation’ in mid-January 2020, foundation installation has hit the halfway mark, with 47 out of a total of 94 foundations installed, DEME said Thursday.

"Despite significant weather downtime in February the installation of the foundations is on schedule for completion in early June. The large carrying capacity of ‘Innovation’, efficient jacking operations and smooth offshore bolting operations lead to record installation cycles," DEME said.

“Together with Ørsted, we will continue our excellent partnership for the remaining foundations. I also would like to take this opportunity to thank the client, our crew and project staff for the great achievement, considering the unprecedented challenges they were all facing,” says Bart De Poorter, General Manager DEME Offshore.

The Borssele 1 & 2 offshore wind farm will be completed in 2020.

Categories: Energy Vessels Industry News Offshore Wind Activity Europe Construction Installation The Netherlands

Related Stories

Siemens Gamesa to Supply Turbines for 1GW Offshore Wind Farm

Acta Marine Takes Delivery of Final CSOV in Four-Vessel Newbuild Program

Seaway7 Starts Cable Installation at Ørsted’s Hornsea 3 Wind Farm

Current News

Indonesia Approves Plan of Development for Geliga Oilfield Six Months After Discovery

First Nordseecluster B Monopiles Arrive at Dutch Port

Dolphin Drilling Closes Rig Sale, Signs India JV Deal with SPM Energy

Arabian Drilling Seals $400M Offshore Vessel Deal with KJO

Subscribe for OE Digital E‑News