DEME Hits Halfway Mark with Borssele Wind Farm Installation

OE Staff
Friday, April 10, 2020

Offshore installation company DEME Offshore has said made strong progress with the installation of the foundations for offshore wind turbines at Ørsted’sBorssele 1 & 2 Offshore Wind Farm in the Dutch North Sea, reaching the halfway mark. 

Having started construction works with offshore installation vessel ‘Innovation’ in mid-January 2020, foundation installation has hit the halfway mark, with 47 out of a total of 94 foundations installed, DEME said Thursday.

"Despite significant weather downtime in February the installation of the foundations is on schedule for completion in early June. The large carrying capacity of ‘Innovation’, efficient jacking operations and smooth offshore bolting operations lead to record installation cycles," DEME said.

“Together with Ørsted, we will continue our excellent partnership for the remaining foundations. I also would like to take this opportunity to thank the client, our crew and project staff for the great achievement, considering the unprecedented challenges they were all facing,” says Bart De Poorter, General Manager DEME Offshore.

The Borssele 1 & 2 offshore wind farm will be completed in 2020.

Categories: Energy Vessels Industry News Offshore Wind Activity Europe Construction Installation The Netherlands

Related Stories

50Hertz, Skyborn Ink Deal for Gennaker Offshore Converter Platforms

Europe Turns to Offshore Wind to Curb Dependence on US Gas

Jan De Nul Leverages Spinergie Data to Guide Offshore Wind Strategy

Current News

GE Vernova Faces Revenue Hit After Offshore Wind Project Setbacks

Gulf Marine Services Extends Middle East Jack-Up Vessel Contracts

Cadeler Lines Up Offshore Wind Foundation Installation Job

50Hertz, Skyborn Ink Deal for Gennaker Offshore Converter Platforms

Subscribe for OE Digital E‑News